How long do building permits take in BC?

Median days from application to issue, by type of work, from the City’s own permit data. Plan crews and quotes around real timelines.

VancouverSurrey · soonBurnaby · soon
Time

Median · all permits

84days

from application to issue, for the 284 permits issued in the last 30 days.

Middle half of permits

23 – 154 days

Nov 2026 vs Dec 2025

30 days faster

Median days by type of work

permits

Median days from application to issue by type of work, Vancouver, last 30 days
TypeMedian daysMiddle halfPermits
Multiplex257 days (middle half 141–320)43
Duplex187 days (middle half 153–216)9
Laneway house137 days (middle half 123–144)10
New house135 days (middle half 92–146)7
Demolition106 days (middle half 51–145)51
Pool / backyard106 days (middle half 84–135)5
Renovation32 days (middle half 7–95)61
Commercial28 days (middle half 14–79)95

Median days, month by month · all permits

What the numbers mean

Read them like a builder would.

Application to issue

The City counts the days from when an application gets a permit number to when the permit is issued. Time before you apply isn’t included.

Median, not average

The median is the middle permit. One stalled tower can wreck an average; it barely moves a median.

Why only Vancouver for now

Vancouver publishes elapsed days with every permit. We’ll add Surrey, Burnaby and others as soon as their data includes application dates.

Permit timing FAQ

Permit timing, answered.

How long does a building permit take in Vancouver?

Over the last 30 days the median was 84 days from application to issue. It depends heavily on the work: renovations were about 32 days and new houses about 135.

When does landscaping happen after a permit?

Usually near the end of the build, many months after the permit is issued. That gap is why permits are an early warning for trades: you can meet the builder long before the yard goes out to quote.

Why is my permit taking longer than the median?

Half of all permits take longer than the median. Complex sites, revisions and missing documents add time. Check with the City for your file.

Where does the data come from?

The City of Vancouver’s open data on issued building permits, which includes the number of days each permit took. We recalculate every morning and show monthly medians.

Permits today, work later

Today’s permit is next season’s job.

PermitRadius sends you the new permits in your radius every Wednesday, so you can meet the builder before the work goes out to quote.

Check my radius — free 14 days free · No card to check · Cancel anytime

Elapsed days as published by the City.